Sunday, July 13, 2008
Gantt Chart
Project:
A Web to Monitor The Weather and Climate Changes Around the World.
Activity A (color) - Team formation, picking a title.
Activity B (color) - Proposal Planning.
Activity C (color) - Tasks being assigned to members.
Activity D (color) - Work Break System diagram, Gantt Chart, network diagram (AOA).
Activity E (color) - Gathering information's and links.
Activity F (color) - Preparation of system requirements.
Activity G (color) - Implementation of project design.
Activity H (color) - Developing the system.
Activity I (color)- Progress report will be uploaded weekly.
Activity J (color)- Troubleshooting, Testing, Debugging and Wrap up.
Activity K (color)- Complete of research paper.
Subscribe to:
Post Comments (Atom)
1 comment:
Your activity for Design and Preparation of Requirement has to be extended to Week 7/8 as you don't have time to finish by Week 4...it's already over....some activities can be made parallel with the development as development takes a long tiem...
Weekly progress report does not have to be counted as an activity as it is miscellaneous.
Post a Comment